Dated: 28/08/2022

Structure Completed

HVAC
Piping work in progress, Cooling tower installation work in progress, Basement ventilation work in progress

Plumbing & Fire Fighting
Plumbing & fire fighting work in progress
Painting work of basement in progress

Electrical Works
Conducting work in progress in the basement
Elevator delivered at site & installation in progress

External Facade work in progress (20% complete)

Others
External development work – rain water harvesting, storm water drainage, main holes & RCC of boundary walls etc. in progress
LT panel panels delivered & installed at site
Facade Cleaning system awarded
DG tender floated
Chillers tender floated
STP Tenders floated

Dated: 25/02/2022

All floors completed (14 floors)

HVAC
Piping work started

Plumbing & Fire Fighting
Plumbing & fire fighting work in progress
Painting work of basement in progress

Electrical Works
Conducting work in progress in the basement
Elevator work awarded to Toshiba elevators

External Facade work awarded

Dated: 03/09/2021

13th floor completed
14th floor work in progress
Plumbing & fire fighting work in progress
Painting work of basement in progress

Dated: 23/06/2021

11th floor completed
12th floor work in progress
Plumbing & fire fighting work in progress
Painting work of basement in progress

Dated: 12/04/2021

9th floor completed
10th floor work in progress
Plumbing & fire fighting work in progress
Painting work of basement in progress

Dated: 01/12/2020

7th floor completed
8th floor work in progress
Tender Floated

Dated: 18/08/2020

Ground & First floor completed
2nd Floor work in progress

Dated: 07/02/2020

Ground floor slab under process.

Dated: 01/05/2018

Basement 3 – Complete
Basement 2 – Casted
Basement 1 – Partly Casted

Dated: 01/01/2018

Basement 3 Casted
Basement 2 Casted
Basement 1 in Progress